Delay in completion nitrogen installation Zuidbroek
The completion of the new nitrogen plant in Zuidbroek will be delayed. The plant consists of 3 units with a capacity of each 60.000 m3 per hour; total capacity 180.000 m3 per hour. The rescheduled completion will now be: • 2 units available as of 1 July 2022; total available capacity 120.000 m3/h. • 3 units available as of 15 August 2022; total available capacity 180.000 m3/h. Please be also informed by the news item on our website. Programme Responsible Parties are expected to carry out their regular activities: monitor your POS and the SBS and balance your portfolio.