Jump to content

Quality Conversion

Today, gas day the 14th of October 2020, tests will take place at a conversion installation that is currently out of order due to maintenance. This might temporarily lead to a higher use of nitrogen than is published as available. The quantity ‘’GC G-gas N2’’ might also increase. If the nitrogen use is in the orange or red area during these tests, we won't publish a REMIT.

Message information
messageType Gas
messageId GTS21X-NL-A-A0A0A-Z-001952_002
eventStatus Active
eventType Other unavailability
eventStart 2020-10-14 08:00:00
eventStop 2020-10-14 18:00:00
unavailabilityType Unplanned
unavailabilityReason -
publicationDateTime 2020-10-14 09:29:22
unitMeasure KWh/h
unavailableCapacity 0
availableCapacity 0
technicalCapacity 0
remarks
balancingZone(s) Nederland - 21YNL----TTF---1
affectedAsset GTS - 21X-NL-A-A0A0A-Z
marketParticipant(s) Gasunie Transport Services B.V. - 21X-NL-A-A0A0A-Z