Today, gas day the 14th of October 2020, tests will take place at a conversion installation that is currently out of order due to maintenance. This might temporarily lead to a higher use of nitrogen than is published as available. The quantity ‘’GC G-gas N2’’ might also increase. If the nitrogen use is in the orange or red area during these tests, we won't publish a REMIT.
|
Message information
|
| messageType |
Gas |
| messageId |
GTS21X-NL-A-A0A0A-Z-001952_002 |
| eventStatus |
Active |
| eventType |
Other unavailability |
| eventStart |
2020-10-14 08:00:00 |
| eventStop |
2020-10-14 18:00:00 |
| unavailabilityType |
Unplanned
|
| unavailabilityReason |
- |
| publicationDateTime |
2020-10-14 09:29:22 |
| unitMeasure |
KWh/h |
| unavailableCapacity |
0 |
| availableCapacity |
0 |
| technicalCapacity |
0 |
| remarks |
|
| balancingZone(s) |
Nederland - 21YNL----TTF---1
|
| affectedAsset |
GTS - 21X-NL-A-A0A0A-Z
|
| marketParticipant(s) |
Gasunie Transport Services B.V. - 21X-NL-A-A0A0A-Z
|