The completion of the new nitrogen plant in Zuidbroek is delayed

Due to recent developments, the schedule below has become uncertain, GTS makes an effort to quickly obtain clarity about a new schedule. The plant consists of 3 units with a capacity of each 60.000 m3 per hour; total capacity 180.000 m3 per hour. The planned startup was January 2023. The rescheduled completion is: • 1 unit available as of 14 February 2023; total available capacity 60.000 m3/h. • 3 units available as of 1 March 2023; total available capacity 180.000 m3/h.

Message information
messageType Other
messageId GTS21X-NL-A-A0A0A-Z-002652_010
eventStatus Active
eventStart 2022-11-04 09:35:00
eventStop
publicationDateTime 2023-01-03 11:45:43
remarks
marketParticipant(s) Gasunie Transport Services B.V. - 21X-NL-A-A0A0A-Z