Update phased delivery of nitrogen from Nitrogen installation Zuidbroek

In line with our previous reports (news item 29 August 2023), the new Zuidbroek nitrogen installation is operational as of Monday 2 October 2023. The capacity will as indicated not be immediately firm available to the market. The commissioning will take place in phases. On 23 November the next 60.000 m3/h was made available to the market on a firm basis. The last 60.000 m3/h will become available on 12 Januari on a firm basis.