Jump to content

Important information about the OBA at entry or exit point 301113: Temporarily deactivation

Due to circumstances GTS is unfortunately forced to temporarily suspend the OBA with effect from 26-11-2018 at 18:00 hrs (Amsterdam time). From that time on the applicable allocation rule will be pro rata (According to Appendix 6 from the Transmission Service Conditions).

Message information
messageType Gas
messageId GTS21X-NL-A-A0A0A-Z-000941_001
eventStatus Active
eventType Transmission system unavailability
eventStart 2018-11-26 18:00:00
eventStop 2018-11-27 00:00:00
unavailabilityType Unplanned
unavailabilityReason Due to technical issues at Gassco's side of the EPT Emden terminal, GTS is forced to suspend the OBA until the technical issues are resolved.
publicationDateTime 2018-11-26 17:49:15
unitMeasure KWh/d
unavailableCapacity 40000000
availableCapacity
technicalCapacity 40000000
remarks
balancingZone(s) Nederland - 21YNL----TTF---1
affectedAsset EMDEN EPT (GASSCO) - 21Z000000000055U
marketParticipant(s) Gasunie Transport Services B.V. - 21X-NL-A-A0A0A-Z